| Guam Construction Update
Motorists are advised to drive cautiously through the construction zones, observe all posted speed limit and construction signs, and carefully heed flaggers (when present). Alternate routes and/or adjusting drive times when feasible are encouraged. Islandwide Primary Roads Paving and Pavement Markings TO-4 Route 10 – Chalan Pago-Ordot/Mangilao Construction activities will continue along Route 10 from December 15 to December 20, 2025. Intermittent lane closures in both directions are expected during work hours: - Monday–Friday: 9:00 AM–4:00 PM
- Saturday: 7:00 AM–6:00 PM
- No construction activities are scheduled for Sunday, December 21, 2025
Locations: Contractor crews will be working at various locations along Route 10 throughout the week, primary areas between Jolene St and Pay-Less. Motorists are advised to expect traffic delays and plan their travel time accordingly. Please slow down and comply with posted speed limits when traveling through the work zone. Remain alert for uneven pavement surfaces and temporary steel plates, and drive safely at all times. Islandwide Primary Roads Paving and Pavement Markings TO-3 Route 8, Mongmong-Toto-Maite Construction activities will continue along Route 8, from the Route 8/7A intersection to Benson, Maite, from December 15 to December 20, 2025. Intermittent lane closures in both directions are expected during work hours: Mon–Fri, 9:00 AM–4:00 PM; Sat, 7:00 AM-6:00 PM.
No construction activities are scheduled for Sunday, December 21, 2025. Islandwide Primary Roads Paving and Pavement Markings TO-3 Route 2A, Santa Rita-Sumai Construction activities will continue along Route 2A, Santa Rita, December 15 to December 19, 2025. Intermittent lane closures in both directions are expected during work hours: Mon–Fri, 9:00 AM–4:00 PM; Sat, 7:00 AM-6:00 PM.
No construction activities are scheduled for Saturday and Sunday, December 20 & 21, 2025. Route 4 Replacement of Ylig Bridge (Phase 2) – Ylig Memorial General construction activities will continue for the Ylig Memorial Project. These activities will not affect the flow of traffic.
The contractor, Korando Corporation, will be working from 7:00 AM till 4:00 PM on weekdays only. No construction activities are scheduled for Saturdays and Sundays. Route 4 Paving from the Tinago River Bridge to Belen Avenue Paving activities will continue along Route 4 starting from the Tinago River Bridge to Belen Avenue. Work will occur between 9:00 AM and 3:00 PM Monday – Friday. The DPW asks motorists to please proceed with caution and remain alert for traffic control signs and work crews. DPW HMC Grass Cutting The DPW HMC crew will be bush/side cutting the following locations, weather permitting: - Roadside maintenance bush cutting Route 27 (Hamburger Road), Harmon
- Roadside maintenance bush cutting Route 27A (Fatima Road), Dededo
- Side cutting Route 9 from the AAFB front gate to Santa Bernadita Church
Work will occur between 9:00 AM and 3:00 PM Monday - Friday. The DPW asks motorists to please proceed with caution and remain alert for traffic control signs and work crews. |