RoadWatch - Week of December 3

Posted: Updated:

by Joan Aguon Charfauros

Guam - Island roadwork continues through some of Guam's busiest villages. Here's your weekly RoadWatch report to help you navigate through some of the tougher spots.

Route 8/10/16 (Tri-Intersection) 
All permanent lanes are open to traffic at the Tri Intersection.  Motorists are cautioned that this area is still a construction zone and there will be intermittent lane closures as items within the Right of Way will still be under construction for the next several weeks.

Route 2 (Umatac) 
Route 2 Cetti Bay Culvert 
Route 2 along the Cetti Bay Culvert will be open to traffic on both lanes. Daytime Lane reduction may occur for short periods of time due to moving equipment. Drivers traveling through this construction area are advised to use caution and observe all traffic control signs placed in advance of the lane closure including all warning, directional, speed and stop signs.

Route 2 Umatac Baseball Culvert 
Motorists traveling through the Umatac Baseball culvert construction site are requested to reduce speed, observe all construction signs and to be aware of workers on the road shoulders. 

Route 2 Cetti Rock Catchments Wall 
Daytime traffic shifts and lane changes continue to be in effect for traffic traveling south of the Cetti Bay Culvert construction area. Drivers are urged to reduce their speed and change lanes when needed.  Delays and increased travel time can be anticipated.

 

Route 2 Sella Bay Culvert 
Route 2 traffic along the Sella Bay Culvert is reduced to one lane. Drivers traveling through this construction area are advised to use caution and observe all traffic control signs placed in advance of the lane closure including all warning, directional, speed and stop signs. 

Route 17 (Talofofo) 
Road construction continues at the intersection of Route 4 and Route 17. Drivers traveling through this area can anticipate shifting lanes, short one lane closures and brief delays. 

Route 4 Togcha and Talofofo Bridges (Talofofo and Inarajan) 
Drivers traveling on Route 4 at the Togcha and Talofofo Bridges are advised that traffic continues to be restricted to one lane.  Temporary stop lights are in place with timing monitored and adjusted to minimize delays.  Increased travel time and short delays should be anticipated while driving through these areas.

 

Route 6A (Murray Road) Asan 
Route 6A Murray Road remains closed while construction work is in progress. Drivers are advised to observe all construction, detour and road closure signs.

Route 4 Ylig Bridge (Yona) 
Pile foundations on the permanent Ylig Bridge on Route 4 will continue to be installed this week.

Due to the proximity of piles to travel lanes, and vibrations generated from this work, intermittent traffic delays and lane closures will be required for the safety of motorists traveling in the area.  The temporary bridge and detour is open to traffic with a posted 15 MPH speed limit. Motorists are requested to observe the posted speed limit and all construction signs.

Route 7A 
Traffic in the construction area of Route 7A is limited to one way west bound from Route 8 to Route 4. Access to businesses and streets along the Route 7A will remain open. 

Motorists are asked to proceed with caution and pay strict attention to traffic control signs posted along the construction area.

For more information contact: 

Guam Transportation Information Center 
Tel: 646-3452 
Fax: 646-3449 
Email:  helpdesk@guamtransportationprogram.com and highways@dpw.guam.gov 
Visit:  www.guamtransportationprogram.com

 

  • NEWS HEADLINESMore>>

  • 15,000 tax refund checks to be sent Monday

    15,000 tax refund checks to be sent Monday

    About 15,000 tax refund checks are being printed tomorrow to be sent out Monday. The Department of Revenue and Taxation, and Department of Administration have started the process to pay out the tax refunds. 

    More >>

    About 15,000 tax refund checks are being printed tomorrow to be sent out Monday. The Department of Revenue and Taxation, and Department of Administration have started the process to pay out the tax refunds. 

    More >>
  • Action taken on over 2,000 CLTC leases

    Action taken on over 2,000 CLTC leases

    Action has been taken on the more than 2,000 Chamorro Land Trust leases deemed voidable. As reported, the AG's opinion issued in May categorized CLTC leases as "voidable" and "null and void." Leases not ratified by the board were deemed "voidable, but notMore >>
    Action has been taken on the more than 2,000 Chamorro Land Trust leases deemed voidable. As reported, the AG's opinion issued in May categorized CLTC leases as "voidable" and "null and void." Leases not ratified by the board were deemed "voidable, but notMore >>
  • Two arrested for Agana Shopping Center riot

    Two arrested for Agana Shopping Center riot

    As an update on another viral fight video, police arrested two people in connection to a riot recorded in the parking lot of the Agana Shopping Center. 19-year-old An Ludwig and a 14-year-old boy are charged with aggravated assault. Police say the incidenMore >>
    As an update on another viral fight video, police arrested two people in connection to a riot recorded in the parking lot of the Agana Shopping Center. 19-year-old An Ludwig and a 14-year-old boy are charged with aggravated assault. Police say the incidenMore >>
Powered by Frankly